Transportation schedule

Transportation Schedule: Week 43


Monday 19 October

  • 2 Hubs via Route 3
  • 2 Nacelles via Route 3
  • 6 Blades via Route 2
  • 10 Towers via Route 1

Tuesday 20 October

No scheduled transportation


Wednesday 21 October

No scheduled transportation


Thursday 22 October

  • 2 Hubs via Route3
  • 2 Nacelles via Route 3
  • 6 Blades via Route 2

Friday 23 October

No scheduled transportation


Transportation Routes

Route 1: wind turbine towers: N1 via Worcester, Laingsburg, Beaufort Wes

Route 2: N9 via Cookhouse, Cradock and Middleburg

Route 3: N10 via Uitenhage, Graaff-Reinet and Middleburg

Transportation Schedule Notes:

  • Transport plan dependent on DOT Transport Permit restrictions (unknown at present).
  • Offload plan dependent on crane pad component layout (to be confirmed).
  • Only unladen / empty transport allowed on Saturdays (assuming DOT approval).
  • In the towns of Riebeeck Kasteel, Riebeeck West, Wolseley, Laingsburg and Beaufort West will be avoided during peak traffic hours, including morning (07:30 to 08:30) and afternoon (16:30 to 18:00).
  • In the town of Middleburg, Meintjies Street will be closed for southbound traffic between Joubert Street and Victoria Street while blade loads are transported slowly through the centre of town, this will take approximately 10 minutes per load and traffic management will be in place during this time.

Transportation Schedule Additional Information

Transport Operation Times

Holiday Periods and Festivals

Temporary Road Closures

 

35

turbines installed and connected to the grid

152m

height of wind turbines

mid 2016

Construction Completed

91 835

homes to be powered
Wind Turbine Facts
FAQs